Managing Your Assigned Locations

What Assigned Locations Are

Your assigned locations are the plants, fields, or runs that EZ Ops downloads to your device. They decide which sites appear in Locations, on your dashboard, and in your offline work — and the number of them is the single biggest factor in how long a sync takes.

Key point: you can change your own assigned locations yourself. You do not need an admin to trim them down or to add a different area back.

Why Fewer Assigned Locations Means Faster Syncs

Every sync clears the locations stored on your device and re-downloads the full list of sites you are currently assigned to, along with their equipment, schedules, inspections, tanks, and reading sheets. Nothing is skipped because you already had it. That means the size of your assignment list sets the size of every sync you do from then on.

Trimming your assignments is worth doing when:

  • Your syncs are slow or time out in weak signal, and you are assigned to more sites than you visit
  • You are working one area this shift and do not need the rest of the organization on your device
  • You rarely need other fields at all — some operators are assigned broadly during onboarding and never narrowed down
  • Saving only changes the server. Sync while online to rebuild your device from the new list
  • Your organization has turned off users assigning themselves to runs. Ask your admin to assign you to a run, or to enable the setting
  • Switching between Plants, Fields, and Runs deletes the assignments held under the previous option. Switch back, re-tick the locations you need, and save
  • Notification routing follows location assignment. Out-of-spec emails, log book acknowledgements, and form and task routing that depend on being connected to a site all stop when you unassign that site. Re-assign the location if you still need to hear about it
  • Trim by area, not site by site - Use Filter by area and unassign whole areas you are not working; picking individual sites out of a long list takes far longer for the same result
  • Sync immediately before and immediately after - The sync before protects work already on your device; the sync after is what actually shrinks it
  • Trim rather than switch - Unticking locations is reversible in a minute. Changing Connect to throws away the whole list, including the per-location settings on it
  • Ask for a run if you work a fixed rotation - A run your admin defines once is faster to assign yourself to each shift than re-ticking plants
  • Never save with nothing assigned - With no assigned locations, Locations and your dashboard come up empty and there is no field work to do
Where to Find Your Assigned Locations

You need to be online for this. The page is part of the online app, not the offline field app.

  1. Open the user menu - Click your own name at the top of the screen
  2. Click Edit Info - The page heading reads Edit User Info, and the browser tab reads User Config
  3. Scroll to Assigned Locations - Click the black Assigned Locations heading to expand the panel
  4. Sync first - Upload any work sitting on your device before you change what is assigned to it
  5. Open Edit Info and expand Assigned Locations - As described above
  6. Leave Connect to alone - Unless you genuinely want to switch to a different assignment type and start over
  7. Narrow the list you are looking at - Use Filter by area to show only the areas you care about (it has its own search box plus Select All and Select None), or type into the search box above the table. Clicking the Assigned or Name column headings sorts the table, which makes it easier to see everything you currently have ticked
  8. Untick the locations you do not need - Use the Assigned checkbox on each row. The checkbox in the grey row directly under Assigned assigns or unassigns every location shown on the current page of the list
  9. Click Save - A confirmation appears: "Are you sure you want to update your assigned locations? Your current settings will be deleted." Click Confirm
  10. Look for the confirmation message - Successfully updated connected sites appears when the change is saved
  11. Sync - Your device does not change until you do

The breadcrumb above the page reads Admin → Users → your name even when you are editing your own record. That is expected — you are in the right place.

The Assigned Locations panel on the Edit User Info page, showing the Connect to dropdown, the Filter by area control, the search box, the location table, and the Save button

Choosing How You Connect

The Connect to dropdown decides what kind of thing you are assigned to. Pick one — you cannot mix them.

Option

What you get

Plants and Associated Locations

The plants you tick, plus every field location underneath them

Fields

The geographic fields you tick, plus every plant and location inside them

Runs

A route of sites your organization has defined. Only appears if your organization allows users to assign themselves to runs

Runs are built by your admin, not by you. You can assign yourself to an existing run, but you cannot create a run or change which sites belong to one. If the rotation you want does not exist as a run yet, ask your admin to build it — then assign yourself to it here.

Changing Connect to wipes your current assignments. Switching from Plants to Fields (or any other combination) deletes every assignment you had under the previous option when you save. Only change it if you intend to rebuild your list from scratch.

How to Reduce Your Assigned Locations How to Set Up for a Different Area

Use the same screen when your shift moves you somewhere else: tick the locations for the new area, untick the ones you are leaving, save, and sync. There is no separate "temporary access" mechanism — adding and removing your own assignments is the mechanism.

Expect the first sync after adding locations to take longer than usual. Adding an assignment also refreshes your tasks, forms, comments, and misc items, so that one sync does more work than the syncs that follow it.

What You Can and Cannot Change Yourself

On the Assigned Locations panel

Can you change it?

Assigned checkbox on any location

Yes

Connect to (Plants / Fields / Runs)

Yes

Out Of Spec Emails for a location you are assigned to

Yes — the checkbox only appears once the row is ticked

Log Book Supervisor, Office Supervisor, Costs Admin

No — visible but read-only for you. An admin sets these

Which sites belong to a run

No — admin only

Assigned Departments (the panel below)

No — admin only

Common Issues

"I unticked locations and saved, but they are still on my device"

"There is no Runs option in the Connect to dropdown"

"I changed Connect to and all my locations disappeared"

"I stopped getting emails or work for an area after trimming my list"

Tips & Recommendations

Remember: Changing Connect to deletes every assignment you held under the previous option, including its Out Of Spec Emails and supervisor settings. Sync any pending work first, and expect to rebuild your list from scratch after switching.